Missing link: Denver International Airport and Transit Center

Building Team Awards

Missing link: Denver International Airport and Transit Center

Gold Award: A new mixed-use transit center fulfills Denver’s 28-year plan to improve access to the nation’s fifth-busiest airport.


By David Barista, Editorial Director | June 8, 2017

Courtesy Scott Frances

This swooping, bird-in-flight, steel-and-glass building is the realization of Denver International Airport’s 1989 master plan to build a public transit center connecting the city’s RTD commuter rail line to the airport. 

The 15-story project is an expansion to the airport’s Jeppesen Terminal and includes three components: a 519-key Westin hotel and conference center, a 82,000-sf plaza with restaurants and retail, and the transit center, which serves more than 18,000 riders daily. 

The Building Team had to overcome a number of hurdles to deliver this project on time and within budget. It had to meet the requirements of three high-profile stakeholders: Starwood (hotel operator), Regional Transportation District (rail line), and the airport. To streamline coordination and speed up decision making, the team enlisted key personnel from each stakeholder to form a small, nimble group. 

The team colocated the critical members and established a real-time data stream of cost and constructability information. This was accomplished with an integrated BIM model that displayed cost-trending information in step with design evolution.

 

The building’s catenary roof and two massive canopies (the one pictured cantilevers 135 feet) required close collaboration among the Building Team members. This canopy is supported solely by two banana-shaped concrete abutments that are 150 feet long and consist of multiple layers of reinforcing cages. Courtesy Scott Frances.

 

The core team was able to quickly problem solve several thorny issues, including: 

  • Coordination with contractors working on adjacent projects, including a new parking structure and a utilities relocation package to within five feet of the hotel.
  • Constructing the 80-foot-clear-span steel catenary roof, which required bucket drops of concrete to avoid concrete avalanching on the undulating surface.
  • Meticulous installation of the facility’s five-story escalator (the tallest in Colorado), which required a complex engineered rigging system to set the escalator just inches over a sloped membrane roofing system. 

 

Building Team – Submitting firm, joint venture contractor MHS Triventure (Mortenson Construction, Hunt Construction, Saunders Construction) Owner Denver International Airport Architect Gensler Architect of record Anderson Mason Dale Associate architect Iron Horse Architects Structural engineers S.A. Miro, Arup Civil engineer Hartwig & Associates MEP engineer ME Engineers

General Information – Size 730,000 sf Cost withheld at owner’s request Construction time November 2012 to April 2016 Delivery method CM/GC

 

Return to the 2017 Building Team Awards landing page

Related Stories

| Aug 29, 2022

Montana becomes first U.S. state to approve 3D printing in construction

Montana is the first U.S. state to give broad regulatory approval for 3D printing in building construction.

Architects | Apr 22, 2022

Top 10 green building projects for 2022

The American Institute of Architects' Committee on the Environment (COTE) has announced its COTE Top Ten Awards for significant achievements in advancing climate action.

Concrete Technology | Apr 19, 2022

SGH’s Applied Science & Research Center achieves ISO 17025 accreditation for concrete testing procedures

Simpson Gumpertz & Heger’s (SGH) Applied Science & Research Center recently received ISO/IEC17025 accreditation from the American Association for Laboratory Accreditation (A2LA) for several concrete testing methods.

2021 Building Team Awards | Jan 14, 2022

First public-private partnership project in Veterans Administration history saves $34 million in costs

LEO A DALY and McCarthy Building Companies head the project team for the Omaha VA Ambulatory Care Center in BD+C’s 2021 Building Team Awards.

Building Team Awards | Dec 8, 2021

A performing arts center celebrates a legendary rocker and his birthplace

Buddy Holly Hall in Texas receives BD+C’s Silver Building Team Award.

Building Team Awards | Dec 7, 2021

A rapid response to a health emergency

Baptist Hospital of Miami’s 233-bed Hope Tower receives BD+C’s Bronze Building Team Award

Building Team Awards | Dec 3, 2021

Putting science on display, thanks to a design-build approach

UC Riverside’s Plant Growth Environments Facility receives BD+C’s Bronze Building Team Award.

Building Team Awards | Dec 2, 2021

An academic ‘precinct’ brings arts and sciences together

Wofford College’s Chandler Center for Environmental Studies receives BD+C’s Silver Building Team Award.

Building Team Awards | Dec 1, 2021

Denver sets the bar for water reclamation and reuse

A new administration building for the city’s water utility company scores Platinum in BD+C’s 2021 Building Team Awards.

2021 Building Team Awards | Nov 17, 2021

Caltech's new neuroscience building unites scientists, engineers to master the human brain

The Tianqiao and Chrissy Chen Institute for Neuroscience at the California Institute of Technology in Pasadena wins a Gold Award in BD+C's 2021 Building Team Awards.

boombox1 - default
boombox2 -
native1 -

More In Category




halfpage1 -

Most Popular Content

  1. 2021 Giants 400 Report
  2. Top 150 Architecture Firms for 2019
  3. 13 projects that represent the future of affordable housing
  4. Sagrada Familia completion date pushed back due to coronavirus
  5. Top 160 Architecture Firms 2021