Unfit planning system means 4,700-year wait for onshore wind

Aaron Morby 12 months ago
Share

The current planning system will fail to deliver the Government’s ambitions to build infrastructure to meet net zero goals and housing needs.

That is the conclusion of a damning report by the Institute for Public Policy Research, which is calling for a complete reset of planning.

It warns that it would take 4,700 years for England to reach the onshore wind capacity called for by government advisers, at the current rate of development.

Progress in England was stalled in 2015 when planning laws were changed to make it more difficult to gain permission for new onshore wind turbines – in what was effectively a ban. 

Since then only 17 onshore wind farms have been approved, generating just 6.7 megawatts of power – equivalent to just 0.02% of the on-shore total needed in England based on National Grid estimates.

The IPPR report calls for restrictions on onshore wind and solar power to be reduced and for local authorities to be compelled to identify land suitable for onshore wind and solar generation. 

It also calls for big planning reforms to get many more houses built, while also moving faster to meet net zero targets.

In particular, the report calls for decisions on new home building to be linked into plans for low-carbon transport networks.

Between them, housing and transport account for over 40% of total emissions, but since 1990 emissions from both sectors have barely declined. 

The report also sheds fresh light on the critical failures of the current system. These include the lack of clear rules for developers and local authorities on when planning permission should be granted, leading to uncertainty and speculative buying of land. 

It argues that local authorities should be compelled to draw up detailed plans for development in their areas that integrate environmental targets, to provide greater certainty.

It proposes that if a planned house building project meets new net zero targets alongside other local requirements, it should be given an automatic green light, removing much of councils’ discretion from the system. 

It calls for national and local house building targets to be reinstated so that councils can be compelled to enable more homes to be built. 

But the report calls for the public to be given a more meaningful say over the future of their local areas than they do at present. 

Luke Murphy, IPPR associate director for energy, climate, housing, and infrastructure, said: “The current planning system in England is not remotely fit for purpose to build a net zero world, restore nature, or meet housing need.

“Fundamental planning reform is needed to accelerate efforts to reduce emissions and restore nature, rollout renewable energy generation, and to deliver the level of housebuilding that the country so desperately needs.”

 

Latest news

Industry rebar supplies at risk from Chatham Docks scheme

ArcelorMittal warns it will be forced to shut Kent facility supplying 30% of UK rebar
2 days ago

Galliford Try wins £70m Oxford immigration centre

Contractor secures job to build 400-bedroom immigration removal centre at Campsfield
2 days ago

18 win £600m North Wales construction framework

Major project lot shared by Galliford Try, Kier and Morgan Sindall, Read and Wynn
2 days ago

Manchester 37-storey student tower approved

Construction to start in early 2025 at old Hotspur Press mill building
2 days ago

Kier chalks up £23m Bradford school job

New Trinity Academy in Bradford to be built in three phases
2 days ago

Subcontractors wanted across Glasgow

Register now to meet buyers at latest Constructionline event
2 days ago

M&E sector leads rise in subcontractor tender activity

Tender activity grows in first quarter but concern about project delays remain
3 days ago

Funding deal for Salford Michigan Tower job

Vermont Construction to build first 34-storey tower for developer X1
3 days ago

Court fight continues for specialist hit by CCJ blunder

Screeding contractor still fighting bureaucracy seven months after incorrect filing
3 days ago

Morgan Sindall bags £60m raft of NHS projects

Mid and South Essex NHS Trust plans six projects
4 days ago

Peri buys shoring and temporary bridge specialist Mabey Hire

Scaffolding and formwork specialist expands offer
4 days ago

Steel contractor Embrace targets £100m revenue

Growing structural steel specialist appoints COO
3 days ago

Vinci/McAlpine go-ahead for £312m Midlands hospitals revamp

Shrewsbury and Telford Hospital NHS Trust gets full business case approval
4 days ago

Lendlease puts construction arm up for sale

After two decades of global expansion Lendlease retreats to Australia
5 days ago

Mount Anvil seals Isle of Dogs estate rebuild

Firm will build 300 new homes at East London's Tiller Road Estate
4 days ago

Northumbria Uni invites bids for £75m CHASE project

12-storey student block to be demolished for new Centre for Health and Social Equity
4 days ago

Civils firm Akela appoints former Robertson director as MD

Framework expert Robert Ogg to lead growth at Scottish contractor
4 days ago

McLaren to build new Hertfordshire primary school

Contractor to prioritise local suppliers on High Leigh Garden Village site
4 days ago

Developer picked for Stafford town centre regeneration

ION Developments will draw up detailed plans for mixed-use Eastgate scheme
4 days ago

Former Crossrail boss Mark Wild to lead HS2

Wild to bear down on spiralling costs and bring rejigged scheme in on time
6 days ago

Receivers in at £125m Manchester tower developer

Domis Construction walked away from scheme following doubts over funding
7 days ago

Costain A1 £260m dualling job finally gets go-ahead

Ministers sat on planning inspectors report for nearly three years
5 days ago

Election delays decision on Lower Thames Crossing

Planning decision on £1.2bn Luton airport expansion also pushed back six months
5 days ago

Caddick steps-in at former Lane End housing job

Contractor to restart phase of £262m scheme hit by administration
5 days ago

Plans in for Leeds iconic Tetley building revamp

Former brewing giant's HQ to become indoor market and offices
5 days ago

BAM wins first phase of North Devon hospital revamp

New staff accommodation to kick-off hospital redevelopment
5 days ago

McAlpine pulls out of £55m Carlisle Citadels project

University of Cumbria starts hunt for replacement contractor
1 week ago

Strabag UK suffers further big trading loss

Austrian contractor is gearing up for major presence in the UK market
1 week ago

Durham Uni picks UPP for £130m student scheme

Firm will deliver 1,000 self-catered bed spaces
1 week ago

Architects now upbeat after 10-months of work gloom

Larger practices see rising workloads in next three months
1 week ago

Contractor services