£9.3bn race starts for National Grid construction partners

Aaron Morby 1 year ago
Share

National Grid Electricity Transmission has fired the starting gun on what will be one of the biggest tender races this year for the construction industry.

The power distributor is planning to shake-up its delivery model for infrastructure in what will be its largest investment programme in generations.

Opting for a collaborative procurement model, The Great Grid Upgrade Partnership will be split into two major lots: covering consultancy and construction works.

Under the new plan, National Grid is seeking 4-6 partners for the construction and services lot as well as two reserve partners.

The prize for the winning firms will be an £8.7bn programme of spending over 8 years.

This will cover the full spread of works from over head line new build and refurbishment to substations, civils and undergrounding construction works.

National Grid plans to share the design, consenting and environmental services lot with two partner consultants and one reserve.

Even this spend on consultants fees will reach nearly £600m.

To set out the new procurement model, National Grid is planning a virtual online bidders day to be held on the week commencing 5 June. (to attend click here for email)

Payment model


It is envisaged that partner firms will work together to innovate and collaborate to deliver the programme, meeting or beating the earliest in service dates for each project.

This will be incentivised through a bespoke commercial model, incentivising all partners at programme level.

Construction partners will hold a notional shareholding for commercial model purposes.

It is currently anticipated that the incentives payable under that model will be the principal source of profit for firms, derived from an additional fee, with the call-off contracts for each package delivered on a cost reimbursable basis with a smaller base fee.

Firms have until 30 June to submit PQQs with tenders likely to be invited in early August from firms shortlisted to bid with a 6-month submission deadline.

John Pettigrew, National Grid chief executive officer said: “The UK has made significant progress in decarbonisation over the last decade.

“But today, we all stand at a critical juncture. The scale of the transformation needed over the next decade and beyond is a level not seen for generations with a far greater level of investment needed over a much shorter timeframe.  Incremental change will not be sufficient – we need a transformative approach.”

Latest news

Third contractor to finally finish £135m Swansea job

Andrew Scott to finish Copr Bay after Buckingham went bust and WIllmott Dixon scaled back involvement
10 hours ago

Top construction chiefs call for more foreign workers

Infrastructure leaders set out blueprint for growth for next Government
2 hours ago

Staff at surface repair specialist Merlin looking for new jobs

Workers let go as contractor "goes under without any notice"
18 hours ago

JRL plans first Manchester 28 storey resi block

Contractor turns developer for £75m private flats project
17 hours ago

Barratt and Springfield deal to deliver new Scottish village

Infrastructure work to start this year on £776m Durieshill site
17 hours ago

Vigil for worker killed at Berkeley site

Worker hit by asphalt paver at Camden Goods Yard site
18 hours ago

Weston Homes names next CEO

Housing expert Peter Gore takes over as group chief executive
18 hours ago

CR Construction (UK) wins £34m historic mill restoration

UK arm of Hong Kong builder to convert Manchester's Talbot Mill to flats
17 hours ago

Industry rebar supplies at risk from Chatham Docks scheme

ArcelorMittal warns it will be forced to shut Kent facility supplying 30% of UK rebar
4 days ago

Galliford Try wins £70m Oxford immigration centre

Contractor secures job to build 400-bedroom immigration removal centre at Campsfield
4 days ago

18 win £600m North Wales construction framework

Major project lot shared by Galliford Try, Kier and Morgan Sindall, Read and Wynn
4 days ago

Manchester 37-storey student tower approved

Construction to start in early 2025 at old Hotspur Press mill building
4 days ago

Kier chalks up £23m Bradford school job

New Trinity Academy in Bradford to be built in three phases
4 days ago

Subcontractors wanted across Glasgow

Register now to meet buyers at latest Constructionline event
4 days ago

M&E sector leads rise in subcontractor tender activity

Tender activity grows in first quarter but concern about project delays remain
5 days ago

Funding deal for Salford Michigan Tower job

Vermont Construction to build first 34-storey tower for developer X1
5 days ago

Court fight continues for specialist hit by CCJ blunder

Screeding contractor still fighting bureaucracy seven months after incorrect filing
5 days ago

Morgan Sindall bags £60m raft of NHS projects

Mid and South Essex NHS Trust plans six projects
5 days ago

Peri buys shoring and temporary bridge specialist Mabey Hire

Scaffolding and formwork specialist expands offer
6 days ago

Steel contractor Embrace targets £100m revenue

Growing structural steel specialist appoints COO
5 days ago

Vinci/McAlpine go-ahead for £312m Midlands hospitals revamp

Shrewsbury and Telford Hospital NHS Trust gets full business case approval
6 days ago

Lendlease puts construction arm up for sale

After two decades of global expansion Lendlease retreats to Australia
7 days ago

Mount Anvil seals Isle of Dogs estate rebuild

Firm will build 300 new homes at East London's Tiller Road Estate
6 days ago

Northumbria Uni invites bids for £75m CHASE project

12-storey student block to be demolished for new Centre for Health and Social Equity
6 days ago

Civils firm Akela appoints former Robertson director as MD

Framework expert Robert Ogg to lead growth at Scottish contractor
6 days ago

McLaren to build new Hertfordshire primary school

Contractor to prioritise local suppliers on High Leigh Garden Village site
6 days ago

Developer picked for Stafford town centre regeneration

ION Developments will draw up detailed plans for mixed-use Eastgate scheme
6 days ago

Former Crossrail boss Mark Wild to lead HS2

Wild to bear down on spiralling costs and bring rejigged scheme in on time
1 week ago

Receivers in at £125m Manchester tower developer

Domis Construction walked away from scheme following doubts over funding
1 week ago

Costain A1 £260m dualling job finally gets go-ahead

Ministers sat on planning inspectors report for nearly three years
7 days ago

Contractor services