Steel erectors working for contractor William Hare at Hinkley have become the latest to down tools for a day at the vast nuclear power station site.

The latest unofficial one-day stoppage yesterday was triggered by existing shift rotation patterns on the site.

Erectors want to change the 11/3 and 10/4 rotation to a regular 10/4 arrangement.

The stoppage follows a developing pattern of industrial unrest among trades in recent weeks.

More than 300 scaffolders working at the Hinkley Point site are now planning a day a week on unofficial strike action after downing tools last Wednesday.

The scaffolders working for BYLOR are understood to be angry about pay rates and shift patterns on the site.

Around 125 mechanical and electrical workers under the MEH Alliance also staged an unofficial walk-out the week before that.

This was sparked by a decision by employers to cut travel allowances by 50%.

Since then, it is understood that the MEH Alliance contractors – Altrad, Balfour Beatty Bailey, Cavendish Nuclear and Doosan Babcock – have agreed to restore travel allowances.

Meanwhile, workers at a Hinkley Point supplier have just secured a pay boost worth up to 13% after seven weeks of action.

More than 150 platers, welders and sheet metal workers at Darchem Engineering, in Stockton-Upon-Tees, walked out in the strike action.

The pay deal will help workers in the cost-of-living crisis.

Andrew Blunt, GMB Organiser, said: “Workers have stood strong together for what they are worth.

“They were offered split deals, real terms pay cuts, and deals that would have delayed any 2024 discussions – leaving them further out of pocket. They rejected them.

“Together they have won a deal that will help them through the cost-of-living crisis.”

Latest news

Direct delivery model pays off as Murphy profit soars to £67m

Group operating margin jumps from 3% to 5% in record year
2 hours ago

Ex-Galliard boss to lead Battersea next building phase

Don O’Sullivan joins as plans advance to start phase 3C of power station redevelopment
31 mins ago

£100m Digbeth 33-storey flats job out to bid

483 flats will be delivered for Clarion housing association
15 mins ago

Van Elle fined £233,000 after piling rig kills driver

Court hears how tragedy was caused by poorly maintained plant
1 hour ago

Renew buys utilities contractor Excalon

Infrastructure giant expand into electricity transmission market with £26m deal
1 hour ago

Planning for new homes plunges to record low

Home builders call for urgent action from incoming government
15 mins ago

JTRE starts £400m 21-floor London tower scheme

Office block and 64 affordable homes to be built at 220 Blackfriars Road site
22 hours ago

R G Carter construction profits up despite 24% revenue fall

Selective client choice help profit jump to £6m from £1m previously
1 day ago

Refurbs power London office work to record high

London Office Crane Survey office work starts exceed 4m sq ft for record third quarter
1 day ago

Knight Build owed money for work on UK’s poshest street

Contractor takes legal action over unpaid bills on new luxury flats complex
1 day ago

Winvic ranks top of May contracts league

Large residential scheme in Leeds caps strong haul of orders
1 day ago

Bid race starts for up £95m repairs to PFI hospital

Roseberry Park Hospital in Middlesbrough hit by serious defects
1 day ago

Building Safety changes slow down construction recovery

Confused market contains paradox of falling workload and contractors claiming they are too busy
1 day ago

Wates rejigs businesses as veteran leader retires

Wates Construction Group MD Paul Chandler to retire at end of year
4 days ago

Scaffolder dies from chemical burns

Tata Chemicals Europe fined £1.125m after death of Altrad scaffolder
4 days ago

M&E firms warn of persistent skills shortages

Shortage of adequately skilled workers blamed for slow growth
4 days ago

Southern Water names consultants for AMP8

Seven firms to share £240m in professional services spend
4 days ago

Construction buyers see momentum building

Contractors gearing-up for future growth as workloads and confidence rise
5 days ago

Bouygues bags £80m London NHS diagnostic centre job

New five-storey scanning facility to be built at West Middlesex University Hospital
5 days ago

London £3bn schools framework out to tender

SMEs allocated slots on London Construction Programme education framework refresh
5 days ago

Berkeley’s £270m Bath gas works scheme approved

House builder plans to build over 600 flats on banks of River Avon
5 days ago

Road sweeper firm Go Plant went down owing suppliers £4.3m

Former staff launch claim for compensation
5 days ago

Openreach fined £1.34m after engineer drowns in river

Court hears how engineer was swept away after falling into water while trying to repair a telephone line
5 days ago

Glencar bags £30m Cambridge lab and office job

Project will be built at Chesterford Research Park life sciences cluster
5 days ago

Bids due in to replace Luton Airport car park destroyed by fire

Big name firms set to battle for £37.5m contract
6 days ago

Plan in for £500m London beds and sheds docks scheme

Work to start in early 2025 on 200 flats, 1,400 student bed and logistic scheme
6 days ago

Operator trapped on crane boom in London site fire

Seven hospitalised after blaze at Bouygues East London building site
7 days ago

Kier FM arm splits into three business streams

Kier Places to extend reach to south coast with reorganisation
6 days ago

Seven secure £3bn United Utilities sewage works deal

Costain, Kier, Murphy and VolkerStevin among winners
6 days ago

Boot gets nod for £110m Walsall warehouse scheme

Work to start on former copper works site in the late Autumn
6 days ago

Contractor services