Align hits key milestone on HS2 Colne Valley viaduct

Aaron Morby 12 months ago
Share

HS2’s main works contractor Align JV has completed the first set of V-shaped bridge piers for what will be the UK’s longest railway bridge

The  V-piers are designed to support the viaduct deck over a series of lakes the Colne Valley Viaduct crosses between the end of the London tunnels and the start of the Chiltern tunnels.

Designed to bear the weight of the 80m wide arches over the lakes, the ‘v-piers’ are twice as large as simpler piers that carry the viaduct over land.

The ‘V piers’ will support a row of elegant arches whose design was inspired by the flight of a stone skimming over the surface of the water.

Cast in place using a series of giant moulds, each pier has a separate tower crane, with a temporary access bridge linking them with the main construction site. Cofferdams were used to hold back the water while the 60m deep foundations were built into the bed of the lakes.

Each pier weighs around 1,800 tonnes and took nine months to complete. To help the engineers master the complex shape of the pier, a mock-up was built off site before work began on the real piers.

The Colne Valley Viaduct – which is being built near Hillingdon – will carry high speed trains more than two miles (3.4km) across the Grand Union Canal, River Colne, local roads and a series of lakes

In total, 11 ‘v-piers’ will support the viaduct over water with a further 45 piers on land.

A 160m long bridge-building machine, known as a ‘launching girder’, will be used to lift the giant concrete deck segments that form the viaduct’s arches into position. Once each section is complete, the machine inches itself forward to build the next stage.

Originally built in 2004, the launching girder was first used during the construction of the Hong Kong East Tsing Yi Viaduct. The machine is named ‘Dominique’ in memory of Bouygues engineer Dominique Droniou who played a leading role in its design.

Deck segments will be placed alternately on each side, using a cantilever approach to balance the structure, as two half-arches are constructed simultaneously. Steel tensioning cables are then threaded through the segments to strengthen the bridge.

Align Project Director, Daniel Altier said:“I am delighted that by working as an integrated team with our supply chain partners, we have been able to erect nearly a third of the deck and complete the first V pier, just a year since Dominique starting operating.”

In the last year, it has installed over 300 out of 1,000 segments required to complete the viaduct deck, installing up to three pairs of segments each day.

To allow for the gentle curve of the viaduct, each of the one thousand segments that form the arches and deck are slightly different – and all are manufactured at a temporary factory set up close by, with direct access to the M25.

Aerial showing the extent of the 3.4km Colne Valley Viaduct once complete

The huge viaduct project is being led by HS2’s main works contractor Align JV – a team made up of Bouygues Travaux Publics, Sir Robert McAlpine and VolkerFitzpatrick working with key suppliers including VSL, Kilnbridge, Tarmac and KVJV.

 

Latest news

Plan in for Manchester ‘upside-down’ 18-storey tower

Landmark cantilevered NXQ building plan for city Northern Quarter
4 hours ago

London 25km Super Sewer hooked up for commissioning

Tideway completes connection to existing Lee Tunnel sewer system
3 hours ago

£200m Lincoln ring-road approved

North Hykeham Relief Road granted planning permission
4 hours ago

£1bn Manchester Airport City plan rebooted as new sci-tech hub

Plan pivots from offices to science and manufacturing campus, called MIX Manchester
24 hours ago

Record results at maintenance specialist Renew

Infrastructure maintenance work continues to pay off for contractor
3 hours ago

Barhale lands £21m shaft scheme for Thames Water

Civils specialist bags latest upgrade deal on Thames Water Ring Main
3 hours ago

Caddick names new north east director

Former Laing O'Rourke project lead joins Yorkshire contractor
5 hours ago

Mount Anvil wins London Camden estate rebuild

Deverloper wins £133m Bacton Phase 2 development in Gospel Oak
1 day ago

London Met Uni seeks firm for £280m estate upgrade

A single partner contractor will deliver 10-year building upgrade plan
1 day ago

Top 30 M&E contractors set for growth – ranking

Growth in data centres and commercial refits creates optimism for year ahead
1 day ago

Race starts for £17m Leicester station redevelopment

City Council aims to restore historic Victoria building
1 day ago

Plant bosses blast “inflexible” police over road bans

Officers spotted outside sites and depots monitoring movements of large kit
4 days ago

Waterproofing firm Pudlo rescued from administration

New owners take on business while sister firm Cemfree sold to SigmaRoc
1 day ago

Construction recovery rained-off in first quarter

Sharp rise in commercial orders offers hope for Summer recovery
4 days ago

Skanska tops April contract wins ranking

London office and data centre projects lift Skanska
4 days ago

Modular builder TopHat managing director departs

Andrew Shepherd leaves Goldman-Sachs backed volumetric business
5 days ago

Balfour wins major Rolls-Royce Derby campus expansion

Masterplan involving 14 building projects will take eight years to complete
4 days ago

Graham nets £60m stands revamp at Lord’s

Construction to start this summer at the home of cricket
5 days ago

Contractors face mental health quiz to win work

Prequalification specialist pushing for mental health questions in assessments
4 days ago

Building boss banned for covid loan abuse

Latest investigation into £50,000 Bounce Back Loan
4 days ago

Ready mix concrete giant files administration notice

Mixit Concrete Limited lodges court notice
5 days ago

Dual student towers plan for Birmingham Gun Quarter

Sama Investments goes to public consultation on 50-storey scheme
5 days ago

15 win £3.5bn Eastern Route Partnership railway deal

Amco, BAM, Morgan Sindall and Story among winners on Eastern Routes Partnership
5 days ago

Expanding Caddick Group tops £500m turnover

Construction drives revenue growth and returns to profit
5 days ago

Structure Tone returns to profit

Contractor confident about prospects in London fit out and refurb market
5 days ago

33 firms secure spots on £3.6bn Northumbrian Water framework

Applebridge, Galliford, Esh and Keltbray may
5 days ago

Construction boss in court over dodgy van deals

Suspended jail sentence after court hears how millions in unexplained payments went through Leeds contractor
5 days ago

Development firm fails hitting London building team for £2.6m

Luxury flats builder Ant Yapi was contracted to redevelop Westminster Tower site
6 days ago

Government set to fund £1bn final HS2 London tunnel drive

Final tunnel drive to be taxpayer funded upfront with cash recouped later
6 days ago

Amazon fires up Big-Box market with £500m job

Next generation triple floor super-shed to be built near Northampton
6 days ago

Contractor services