Watchdog MPs blast “floundering” HS2 Euston Station plans

Grant Prior 11 months ago
Share

The Department for Transport still does not know what it is trying to achieve with the HS2 station at Euston despite spending over eight years planning and designing it.

A damning report by watchdog MPs on the Public Accounts Committee said the scheme is “floundering” as cost estimates for its construction rise to £4.8bn from an original £2.6bn.

The government announced in March that work on the station will be paused for two years in a bid to cut costs.

Dame Meg Hillier MP, Chair of the Committee, said: “The HS2 Euston project is floundering. This is a multi-billion pound scheme which has already caused major disruption to the local community put on pause.

“The pause, ostensibly to save money, is not cost free – mothballing and possible compensation for businesses which have lost work will all need to be added to the HS2 tally. The Government must now be clear what it is trying to achieve with this new station, and how it will benefit the public.

“Our report finds that a wildly unrealistic budget for HS2 Euston was set in 2020 in the expectation that it would be revised.

“The Government must demonstrate that that it is not just repeating the same mistakes of unrealistic costings. HS2 Euston has shown us that forging ahead over-optimistically in an unclear direction is clearly not the right approach.”

The report added:” The PAC is also unconvinced that the impact for the DfT’s supply chain, in particular for smaller businesses involved in the works, will be mitigated by their employment elsewhere on the HS2 scheme.

“Questions also remain as to how the Government will manage high levels of inflation on the HS2 programme. The PAC’s inquiry heard the HS2 project is seeing 30% to 40% swings in the cost of raw materials.”

Latest news

Lendlease puts construction arm up for sale

Radical global restructure to raise £2.3bn and focus on Australia
3 hours ago

Former Crossrail boss Mark Wild to lead HS2

Wild to bear down on spiralling costs and bring rejigged scheme in on time
21 hours ago

Receivers in at £125m Manchester tower developer

Domis Construction walked away from scheme following doubts over funding
2 days ago

Costain A1 £260m dualling job finally gets go-ahead

Ministers sat on planning inspectors report for nearly three years
8 hours ago

Election delays decision on Lower Thames Crossing

Planning decision on £1.2bn Luton airport expansion also pushed back six months
8 hours ago

Caddick steps-in at former Lane End housing job

Contractor to restart phase of £262m scheme hit by administration
8 hours ago

Plans in for Leeds iconic Tetley building revamp

Former brewing giant's HQ to become indoor market and offices
8 hours ago

BAM wins first phase of North Devon hospital revamp

New staff accommodation to kick-off hospital redevelopment
8 hours ago

McAlpine pulls out of £55m Carlisle Citadels project

University of Cumbria starts hunt for replacement contractor
5 days ago

Strabag UK suffers further big trading loss

Austrian contractor is gearing up for major presence in the UK market
4 days ago

Durham Uni picks UPP for £130m student scheme

Firm will deliver 1,000 self-catered bed spaces
4 days ago

Architects now upbeat after 10-months of work gloom

Larger practices see rising workloads in next three months
4 days ago

Motorist dies after collision with road paver

Police Scotland investigating fatal crash
5 days ago

McLaren Living appoints HG Construction for £69m scheme

Build to Rent scheme will transform former vacant car park site in Leeds city centre
5 days ago

Squibb liquidator probes £2m of “missing” plant

Machinery, cars and scrap metal have disappeared at demolition specialist
5 days ago

Galliford Try to re-enter affordable homes market

Contractor sets out new five-year plan to build margin to 4%
5 days ago

Former Sellar chief to lead civils contractor Kilnbridge

Owen Dannatt joins as new CEO as founder Dermot McDermott becomes Chairman
5 days ago

Hunt starts for nuclear fusion plant construction partner

Fusion energy plant to be built at West Burton coal power station site.
5 days ago

National Grid raises £7bn for big infrastructure upgrade

Rights issue to fund a major round of capital investment in energy infrastructure
5 days ago

Grenfell police probe to last at least until end of 2025

19 companies and 58 individuals could eventually face charges
6 days ago

Mace confirmed on £100m London office retrofit

Work underway on Helical's 100 New Bridge Street job near Ludgate Circus
6 days ago

Wylfa chosen for next big nuclear power station build

Government names Anglesey site for a large-scale gigawatt nuclear power plant.
6 days ago

Bowmer & Kirkland trading profit halves

Contractor buys HVAC specialist Adcock despite challenging market
6 days ago

Piling specialist Van Elle plans further job cuts

Piling specialist plans further cost savings in face of lower demand
6 days ago

Civils contractor A Catlow files administration notice

High voltage cable specialist lodges court notice
6 days ago

Green light for ARC Oxford lab campus

Work to start later this year on £40m Ascent building job
6 days ago

Stonehenge tunnel hit by another legal delay

Court upholds latest appeal against £1.7bn scheme by campaigners
1 week ago

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
1 week ago

40% affordable homes target for Labour’s new towns

Labour pledges to select new town sites by end of first year
1 week ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
1 week ago

Contractor services