Unfit planning system means 4,700-year wait for onshore wind

Aaron Morby 11 months ago
Share

The current planning system will fail to deliver the Government’s ambitions to build infrastructure to meet net zero goals and housing needs.

That is the conclusion of a damning report by the Institute for Public Policy Research, which is calling for a complete reset of planning.

It warns that it would take 4,700 years for England to reach the onshore wind capacity called for by government advisers, at the current rate of development.

Progress in England was stalled in 2015 when planning laws were changed to make it more difficult to gain permission for new onshore wind turbines – in what was effectively a ban. 

Since then only 17 onshore wind farms have been approved, generating just 6.7 megawatts of power – equivalent to just 0.02% of the on-shore total needed in England based on National Grid estimates.

The IPPR report calls for restrictions on onshore wind and solar power to be reduced and for local authorities to be compelled to identify land suitable for onshore wind and solar generation. 

It also calls for big planning reforms to get many more houses built, while also moving faster to meet net zero targets.

In particular, the report calls for decisions on new home building to be linked into plans for low-carbon transport networks.

Between them, housing and transport account for over 40% of total emissions, but since 1990 emissions from both sectors have barely declined. 

The report also sheds fresh light on the critical failures of the current system. These include the lack of clear rules for developers and local authorities on when planning permission should be granted, leading to uncertainty and speculative buying of land. 

It argues that local authorities should be compelled to draw up detailed plans for development in their areas that integrate environmental targets, to provide greater certainty.

It proposes that if a planned house building project meets new net zero targets alongside other local requirements, it should be given an automatic green light, removing much of councils’ discretion from the system. 

It calls for national and local house building targets to be reinstated so that councils can be compelled to enable more homes to be built. 

But the report calls for the public to be given a more meaningful say over the future of their local areas than they do at present. 

Luke Murphy, IPPR associate director for energy, climate, housing, and infrastructure, said: “The current planning system in England is not remotely fit for purpose to build a net zero world, restore nature, or meet housing need.

“Fundamental planning reform is needed to accelerate efforts to reduce emissions and restore nature, rollout renewable energy generation, and to deliver the level of housebuilding that the country so desperately needs.”

 

Latest news

Construction buyers see fastest growth for 14 months

Commercial building work leads the way in April
44 mins ago

Go Modular Technologies files administration notice

Southampton bespoke volumetric specialist employs around 60 staff
4 hours ago

Cladding firm went down owing supply chain £7.7m

Debts revealed at Everton stadium cladding contractor Alucraft Systems Ltd
4 hours ago

Rydon dogged by legacy fire safety remediation costs

£19m spent on fire safety remediation work to date
4 hours ago

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
4 days ago

Trio of builders win King’s Award for sustainability

Henry Brothers, Willmott Dixon and ZED Pods recognised for sustainability
3 hours ago

Kent police seize huge haul of stolen site tools

Hunt for power drill fitted with tracker busts tool theft ring
4 hours ago

Robertson names new Northern construction chiefs

Ian Phillips promoted and Ricky Brown joins from Morgan Sindall
4 hours ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
4 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
4 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
4 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
4 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
5 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
5 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
5 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
5 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
6 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
5 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
6 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
5 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
5 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
6 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
6 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
7 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
6 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
6 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
6 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
1 week ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
1 week ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
1 week ago

Contractor services