Delay on new 2.0 hospital design stalls big build plan

Aaron Morby 10 months ago
Share

The Government needs to quadruple planned spending on its new hospital programme to get close to meeting already revised building plans.

Midland Metropolitan University Hospital, due to open next year, is 67% over budget
Midland Metropolitan University Hospital, due to open next year, is 67% over budget

A thorough audit of progress on the Boris Johnson Government’s commitment to build 40 new hospitals by 2030 has revealed serious flaws in progress to date.

The National Audit Office report warns the Government will miss its target by 2030 and urged NHS officials to speed up delivery of the second phase of projects.

Much of the major project element of the building programme has been loaded into 2025 starts, yet the plans to standardise design to modularise and cut costs of the next generation of hospitals has failed to materialise.

While the new 2.0 standard design for major hospitals is hoped to be completed by May next year, all major schemes seeking outline budget approval have been stalled by the design delay.

According to a new NAO report the whole programme is looking in serious ill health, due to inflation already driving up costs on smaller committed to projects and the lack of design certainty needed for accurate projected building cost savings on the next generation of larger hospitals expected to cost over £1bn each.

Auditors are calling on Government to push forward smaller schemes in the second phase due to start next year to avoid a serious logjam on the progress of the major hospital schemes being brought through in phase three.

The report warns that the four contractors singled out to deliver the programme –  ISG, Kier, Laing O’Rourke and Wates – could face serious capacity constraints if the throughput of projects is bunched.

Meg Hillier MP, Chair of the Committee of Public Accounts: “English hospitals are in poor condition, after years of underinvestment.

“Today’s NAO report shows the government’s woeful lack of progress against its commitment to build 40 new hospitals by 2030.

“It has failed to even begin construction on any of the new hospitals in its second cohort which it thought were quick wins.”

She added: “The Department of Health and Social Care has been trying to move the goalposts so it can claim it has met its target. Patients and clinicians are going to have to wait much longer than they expected before their new hospitals are completed.”

When the health department officially set out the plan in October 2020, eight hospital construction projects already underway were not included in the target. But recent government statements about building 40 new hospitals include these eight projects, referred to as “legacy hospitals”.

Also last May, the government changed the scope of the programme to include hospitals in urgent need of repairs, including five judged to be at risk of collapse because of crumbling concrete infrastructure.

New hospital programme progress and budgets


First phase – eight legacy projects


Second Phase – due to complete construction by early 2028


Phase three  –  bulk of major projects

Phase four

NAO recommendations to DHSC, NHS England and government more widely include:

  • Announcements about major capital programmes extending over more than one spending review period should fully reflect known uncertainties.
  • DHSC should choose future hospital construction projects transparently and keep full records.
  • Further bunching of construction schemes should be avoided.
  • NHP should reconsider assumptions that may result in ‘minimum viable product’ future hospitals being too small.

Gareth Davies, the head of the NAO said: “The programme has innovative plans to standardise hospital construction, delivering efficiencies and quality improvements.

“However, by the definition the government used in 2020 it will now deliver 32 rather than 40 new hospitals by 2030.

“Delivery so far has been slower than expected, both on individual schemes and in developing the Hospital 2.0 template, which has delayed programme funding decisions.

“There are some important lessons to be drawn for major programmes from the experience of the New Hospital Programme so far.

“These include strengthening the business case process to improve confidence on affordability and delivery dates, and improving transparency for key decisions.”

Latest news

Plant bosses blast “inflexible” police over road bans

Officers spotted outside sites and depots monitoring movements of large kit
2 days ago

Construction recovery rained-off in first quarter

Sharp rise in commercial orders offers hope for Summer recovery
2 days ago

Skanska tops April contract wins ranking

London office and data centre projects lift Skanska
2 days ago

Modular builder TopHat managing director departs

Andrew Shepherd leaves Goldman-Sachs backed volumetric business
3 days ago

Balfour wins major Rolls-Royce Derby campus expansion

Masterplan involving 14 building projects will take eight years to complete
2 days ago

Graham nets £60m stands revamp at Lord’s

Construction to start this summer at the home of cricket
3 days ago

Contractors face mental health quiz to win work

Prequalification specialist pushing for mental health questions in assessments
2 days ago

Building boss banned for covid loan abuse

Latest investigation into £50,000 Bounce Back Loan
2 days ago

Ready mix concrete giant files administration notice

Mixit Concrete Limited lodges court notice
3 days ago

Dual student towers plan for Birmingham Gun Quarter

Sama Investments goes to public consultation on 50-storey scheme
3 days ago

15 win £3.5bn Eastern Route Partnership railway deal

Amco, BAM, Morgan Sindall and Story among winners on Eastern Routes Partnership
3 days ago

Expanding Caddick Group tops £500m turnover

Construction drives revenue growth and returns to profit
3 days ago

Structure Tone returns to profit

Contractor confident about prospects in London fit out and refurb market
3 days ago

33 firms secure spots on £3.6bn Northumbrian Water framework

Applebridge, Galliford, Esh and Keltbray may
3 days ago

Construction boss in court over dodgy van deals

Suspended jail sentence after court hears how millions in unexplained payments went through Leeds contractor
3 days ago

Development firm fails hitting London building team for £2.6m

Luxury flats builder Ant Yapi was contracted to redevelop Westminster Tower site
4 days ago

Government set to fund £1bn final HS2 London tunnel drive

Final tunnel drive to be taxpayer funded upfront with cash recouped later
4 days ago

Amazon fires up Big-Box market with £500m job

Next generation triple floor super-shed to be built near Northampton
4 days ago

Stricken road sweeper specialist rescued

Parts of hire specialist Go Plant bought out of administration by Sweeptech
4 days ago

Costain highways lead joins Buro Happold

Paula Gough appointed to UK Development Director for Infrastructure
4 days ago

G&H Group lands £20m+ M&E package from JJ Rhatigan

100-strong specialist team to start on West London site next week
4 days ago

Bidding open for £800m professional services deal

Procure Partnerships encourages SMEs to bid with 9 regional lots
4 days ago

Construction buyers see fastest growth for 14 months

Commercial building work leads the way in April
5 days ago

Go Modular Technologies files administration notice

Southampton bespoke volumetric specialist employs around 60 staff
5 days ago

Cladding firm went down owing supply chain £7.7m

Debts revealed at Everton stadium cladding contractor Alucraft Systems Ltd
5 days ago

Rydon dogged by legacy fire safety remediation costs

£19m spent on fire safety remediation work to date
5 days ago

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
1 week ago

Trio of builders win King’s Award for sustainability

Henry Brothers, Willmott Dixon and ZED Pods recognised for sustainability
5 days ago

Kent police seize huge haul of stolen site tools

Hunt for power drill fitted with tracker busts tool theft ring
5 days ago

Robertson names new Northern construction chiefs

Ian Phillips promoted and Ricky Brown joins from Morgan Sindall
5 days ago

Contractor services