HS2 delay adds £360m to overall cost

Aaron Morby 11 months ago
Share

The two-year programme delay imposed on key sections of HS2 phase 1 will inflate the overall project cost by at least £360m.

The first stab at what the true cost of delaying works to control day-to-day project costs has emerged in leaked internal Government documents.

The briefing also warns the two-year pause to construction work on key sections at Euston and phase 2a between Birmingham and Crewe will actually set work back 3.5 years when taking into account re-mobilisation to full capacity.

Earlier this week, rail minister Huw Merriman admitted that the cost of rebuilding Euston had risen by £2.2bn to £4.8bn.

In his report on the project he also warned that the Euston terminus was not affordable at that price.

The industry has always argued that a project delay could only ever inflate the delivery budget even if it buys time to revisit the costly Euston terminus design for a third time to re-engineer down costs.

A spokesperson for the High Speed Rail Group, representing suppliers and contractors, said: “As we said when the two-year delay was announced in March this year, the cheapest way to deliver HS2 is quickly. 

“Once complete the railway will be a vital new artery for the United Kingdom which adds necessary capacity for people and goods, while getting passengers off planes and onto trains.

“This is necessary both for economic growth and to meet the UK’s net zero ambitions.

“We need ministers to urgently agree a long-term plan to deliver this vital piece of infrastructure.”

Latest news

Construction recovery rained-off in first quarter

Sharp rise in commercial orders offers hope for Summer recovery
2 hours ago

Skanska tops April contract wins ranking

London office and data centre projects lift Skanska
3 hours ago

Modular builder TopHat managing director departs

Andrew Shepherd leaves Goldman-Sachs backed volumetric business
19 hours ago

Balfour wins major Rolls-Royce Derby campus expansion

Masterplan involving 14 building projects will take eight years to complete
2 hours ago

Graham nets £60m stands revamp at Lord’s

Construction to start this summer at the home of cricket
21 hours ago

Contractors face mental health quiz to win work

Prequalification specialist pushing for mental health questions in assessments
2 hours ago

Building boss banned for covid loan abuse

Latest investigation into £50,000 Bounce Back Loan
2 hours ago

Ready mix concrete giant files administration notice

Mixit Concrete Limited lodges court notice
1 day ago

Dual student towers plan for Birmingham Gun Quarter

Sama Investments goes to public consultation on 50-storey scheme
1 day ago

15 win £3.5bn Eastern Route Partnership railway deal

Amco, BAM, Morgan Sindall and Story among winners on Eastern Routes Partnership
1 day ago

Expanding Caddick Group tops £500m turnover

Construction drives revenue growth and returns to profit
1 day ago

Structure Tone returns to profit

Contractor confident about prospects in London fit out and refurb market
1 day ago

33 firms secure spots on £3.6bn Northumbrian Water framework

Applebridge, Galliford, Esh and Keltbray may
1 day ago

Construction boss in court over dodgy van deals

Suspended jail sentence after court hears how millions in unexplained payments went through Leeds contractor
1 day ago

Development firm fails hitting London building team for £2.6m

Luxury flats builder Ant Yapi was contracted to redevelop Westminster Tower site
2 days ago

Government set to fund £1bn final HS2 London tunnel drive

Final tunnel drive to be taxpayer funded upfront with cash recouped later
2 days ago

Amazon fires up Big-Box market with £500m job

Next generation triple floor super-shed to be built near Northampton
2 days ago

Stricken road sweeper specialist rescued

Parts of hire specialist Go Plant bought out of administration by Sweeptech
2 days ago

Costain highways lead joins Buro Happold

Paula Gough appointed to UK Development Director for Infrastructure
2 days ago

G&H Group lands £20m+ M&E package from JJ Rhatigan

100-strong specialist team to start on West London site next week
2 days ago

Bidding open for £800m professional services deal

Procure Partnerships encourages SMEs to bid with 9 regional lots
2 days ago

Construction buyers see fastest growth for 14 months

Commercial building work leads the way in April
3 days ago

Go Modular Technologies files administration notice

Southampton bespoke volumetric specialist employs around 60 staff
3 days ago

Cladding firm went down owing supply chain £7.7m

Debts revealed at Everton stadium cladding contractor Alucraft Systems Ltd
3 days ago

Rydon dogged by legacy fire safety remediation costs

£19m spent on fire safety remediation work to date
3 days ago

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
7 days ago

Trio of builders win King’s Award for sustainability

Henry Brothers, Willmott Dixon and ZED Pods recognised for sustainability
3 days ago

Kent police seize huge haul of stolen site tools

Hunt for power drill fitted with tracker busts tool theft ring
3 days ago

Robertson names new Northern construction chiefs

Ian Phillips promoted and Ricky Brown joins from Morgan Sindall
3 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
1 week ago

Contractor services