Risk of collapse in ‘high winds’ shuts Caledonian Modular schools

Aaron Morby 9 months ago
Share

The Government has revealed that schools built by offsite specialist Caledonian Modular may not be able to withstand high winds or heavy snow loading.

Buckton Fields Primary School in Northampton is the latest to be shut over structural integrity fears
Buckton Fields Primary School in Northampton is the latest to be shut over structural integrity fears

Education minister Nick Gibb revealed concerns about structural integrity as a third school was officially closed in the growing crisis.

The latest school to be stricken with closure is Buckton Fields Primary School in Northampton.

The primary school, which was built by Caledonian Modular and has been open for two years, has now been told by the Department for Education that it cannot open for the new term.

School owner Preston Hedges Trust chief executive, Paul Watson, said: “We were naturally shocked to be told by the Department for Education that we were unable to use the school building at Buckton Fields at the start of this coming new school year.”

In an interview with BBC Essex education minister Nick Gibb said that the DfE had carried out a review which had identified problems with the modular design of the schools.

“[The review] identified issues that related to the structural integrity of the buildings, weakening its ability for example to withstand extreme events such as high winds or a big snowfall or indeed a collision from a vehicle,” he said.

Asked if the buildings could collapse because of extreme weather, such as a winter storm, Gibb said: “That’s the risk and we are not prepared to take any risk with children, or teachers or staff’s lives in a school, and that’s why we intervened very quickly.”

The latest primary school closure follows orders to stop two secondary schools from reopening for the new term.

These are Haygrove School in Bridgwater, Somerset and Sir Frederick Gibberd College in Harlow, Essex.

Both these secondary schools were built by Caledonian Modular in a single £38m batched deal under the Department for Education’s £3bn modular framework, set up in 2020 to fastrack construction and deliver better value for money.

Two further primary schools in Cornwall only part-built as Caledonian Modular when it fell into administration in March 2022 were also completely demolished earlier this year.

At the time, the buildings were condemned after construction issues were uncovered at both Launceston and Newquay primary school projects.

 

Latest news

Squibb liquidator probes £2m of “missing” plant

Machinery, cars and scrap metal have disappeared at demolition specialist
2 hours ago

Galliford Try to re-enter affordable homes market

Contractor sets out new five-year plan to build margin to 4%
1 hour ago

Former Sellar chief to lead civils contractor Kilnbridge

Owen Dannatt joins as new CEO as founder Dermot McDermott becomes Chairman
1 hour ago

Hunt starts for nuclear fusion plant construction partner

Fusion energy plant to be built at West Burton coal power station site.
1 hour ago

National Grid raises £7bn for big infrastructure upgrade

Rights issue to fund a major round of capital investment in energy infrastructure
55 mins ago

Grenfell police probe to last at least until end of 2025

19 companies and 58 individuals could eventually face charges
11 hours ago

Mace confirmed on £100m London office retrofit

Work underway on Helical's 100 New Bridge Street job near Ludgate Circus
22 hours ago

Wylfa chosen for next big nuclear power station build

Government names Anglesey site for a large-scale gigawatt nuclear power plant.
1 day ago

Bowmer & Kirkland trading profit halves

Contractor buys HVAC specialist Adcock despite challenging market
1 day ago

Piling specialist Van Elle plans further job cuts

Piling specialist plans further cost savings in face of lower demand
1 day ago

Civils contractor A Catlow files administration notice

High voltage cable specialist lodges court notice
1 day ago

Green light for ARC Oxford lab campus

Work to start later this year on £40m Ascent building job
1 day ago

Stonehenge tunnel hit by another legal delay

Court upholds latest appeal against £1.7bn scheme by campaigners
2 days ago

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
2 days ago

40% affordable homes target for Labour’s new towns

Labour pledges to select new town sites by end of first year
2 days ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
2 days ago

Surgo Construction went down owing £4.5m

Biggest creditor is Bellway Homes after dispute on housing job
2 days ago

Vistry seals £157m West London housing deal

Around 575 homes to be built at Merrick Place scheme in Ealing
2 days ago

Streamlined Watkin Jones returns to profit in first half

Multi-room specialist sees secured work pipeline hit £1.4bn
2 days ago

Bellway hires ex-brickie as group construction chief

James Griffin to oversee move to the Future Homes Standard and timber frame.
2 days ago

Persimmon under fire for delays to £10m relief road

West Suffolk Council serves Breach of Condition Notices after timetable slips again
2 days ago

BAM wins £33m Kent secondary school job

Replacement Swanley academy to be built at live school site
2 days ago

Aluminium cladding specialist collapses

Melton Mowbray-based firm worked for several main contractors
3 days ago

Brickwork contractor Lee Marley returns to profit

Affordable and rental homes demand lifts brickwork contractor
3 days ago

Housing contractor Durkan suffers second year of losses

More fire safety provisions tip firm into £3.9m loss
3 days ago

Farrans makes breakthrough on tricky tunnel job

Tunnel under Tees latest part of new £155m water pipeline job
3 days ago

Heidelberg buys aggregates and earthworks specialist B&A

Latest deal follows acquisition of Mick George
3 days ago

Flagship biodiversity net gain scheme flawed

NAO warns Government's flagship green development scheme at risk of failure
6 days ago

Plan in for £3bn Lincolnshire mega data centre

3.3m sq ft Humber Tech Park will be one of Europe's largest data centres
6 days ago

Green light for Digbeth 1,300 homes scheme

Warner’s Fields scheme to start with excavation and landscaping of the River Rea
6 days ago