Costs soar at Manchester £357m town hall job

Aaron Morby 10 months ago
Share

Lendlease’s restoration of Manchester’s grade one-listed town hall is running two years late and has broken the contingency budget.

Rampant construction inflation, knock-on costs of delays from Covid and more stringent fire testing of materials are being blamed for pushing the project seriously over budget.

With restoration work around 60% complete, the project is now running £63m over budget with contingency funds used up.

Lendlease has asked for £29m immediate interim cash to complete some key works needed before a revised full and final cost estimate can be produced for the city council.

The extra funding will see the project budget rise to around £357m.

The project programme, which was due to complete in 2024, is presently pencilled in for 2026, although the city council said Lendlease would be pulling out the stops to bring the latest forecast completion date forward.

But the final cost and programme timeline will not be known until the start of 2024.

In a statement, the council said: “By the end of this year ongoing work to open up the Town Hall roof – with the scope for further discoveries being made about the condition of the building which may mean more extensive work than originally anticipated is required – will be far enough advanced to give much better certainty about final costs and timescales.

“A request for whatever further additional funding is needed to complete the project will then be made in January 2024. This would also be funded through borrowing.”

Deputy Council Leader Cllr Luthfur Rahman said: “The length and complexity of the project is such that it has been buffeted by some unprecedented challenges, the cost impacts of which are magnified because of the sheer scale involved.

“Nobody is pretending this has been easy but the end result will be something truly special, a source of pride and a remarkable asset for Manchester.”

 

Latest news

Osborne staff start looking for new jobs

"Open to Work" flags appear on LinkedIn profiles
2 days ago

Plan rejected for 42-storey tower above historic building

Councillor describes as ludicrous plan to build 300 flats above Georgian mansion
2 days ago

Ventilation deal could hike product prices for contractors

Watchdogs at CMA launch probe after duct firm acquires rival
2 days ago

Tide gets go-ahead for London 412 student flats scheme

Volumetric developer secures planning for West Ealing project
2 days ago

Green light for £75m Friar Gate Goods Yard in Derby

Construction set to start this summer on revamp of historic buildings
2 days ago

Robertson to deliver £45m Newcastle NHS Trust works

Capital works will be focused on Freeman Hospital and the Royal Victoria Infirmary sites
2 days ago

Winners named for £2bn Healthy Homes framework

CHIC reveals line-up of over 40 firms for net zero and building safety works
2 days ago

Plan lodged for tallest skyscraper outside London

Developer Salboy submits plan for 76-storey Manchester resi tower
3 days ago

Curo starts £170m race for new homes framework

Bath housing association plans to build up to 300 homes a year
3 days ago

Gove approves major Cambridge North mixed-use scheme

Government backs controversial scheme of 424 flats and 600,000 sq ft of tech and lab space
3 days ago

Pontins holiday park to house Sizewell C builders

Suffolk holiday park to house 500 nuclear construction workers
3 days ago

Adrian Bloor targets 1,000 homes-a-year

Expansion plans after major investment into challenger house building business HarperCrewe
3 days ago

Housing firm fined £528,000 after cable strike

Maintenance workers given no information on underground services
3 days ago

Berkeley subbies face six weeks without payments

Introduction of new finance software means payment hiatus for suppliers
4 days ago

Pagabo reveals 56 winners of latest £1.6bn retrofit deal

Decarbonisation Solutions Framework launched: Full list of winners
4 days ago

Go-ahead for £100m Liverpool Love Lane flats

500-flat scheme will be built across four blocks in Vauxhall area of city
4 days ago

Unions win HS2 site access battle at Old Oak Common job

Skanska, Costain, Strabag JV now the last denying unions access to HS2 sites
4 days ago

Contractors jack 1,100t viaduct into place in 13-hour operation

158m-long composite deck structure jacked into place 10-hours ahead of schedule
4 days ago

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
5 days ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
5 days ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
5 days ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
5 days ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
5 days ago

Higgins wins £75m Peabody Passive House job

Latest phase of Deptford Landings to start construction
5 days ago

Contractors and unions agree Sizewell C working deal

New deal offers improved sick pay and parental leave over Hinkley Point deal
5 days ago

Competition chiefs win legal fight for more construction raids

High Court rules CMA officials can raid a domestic property as part of investigation
6 days ago

More Osborne companies file administration notices

Three more divisions lodge notices with court
6 days ago

McLaren wins multi-storey urban logistics contract

South London win with British Land is pioneering urban logistics hub
6 days ago

Big social housing schemes at risk over funding uncertainty

Housing associations warn uncertainty over public funding beyond 2026 is curbing new schemes
6 days ago

Kier wins Worcestershire town centre renewal

Firm secures Bromsgrove commercial and cultural hub project
6 days ago

Contractor services