Phoenix Airport Concourse Cruises to Completion
ENR Construction
JUNE 23, 2022
Project team uses construction manager at-risk delivery to add eight gates and renovate existing terminal space at Phoenix Sky Harbor Airport.
This site uses cookies to improve your experience. By viewing our content, you are accepting the use of cookies. To help us insure we adhere to various privacy regulations, please select your country/region of residence. If you do not select a country we will assume you are from the United States. View our privacy policy and terms of use.
ENR Construction
JUNE 23, 2022
Project team uses construction manager at-risk delivery to add eight gates and renovate existing terminal space at Phoenix Sky Harbor Airport.
Lets Build
FEBRUARY 2, 2022
A report commissioned by the University of Cambridge’s Centre for Digital Built Britain (CDBB) and prepared by KPMG focused on the value of Information Management within construction and infrastructure sectors. VolkerWessels UK participation in the value of information management in construction report. Improved performance.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
ENR Construction
MARCH 7, 2019
In delivering Orlando International Airport’s $262-million South Airport Automated People Mover Complex via the construction management-at-risk approach—a first for the owner—contractor Hensel Phelps would be tasked with an unusually demanding coordination effort.
ENR Construction
OCTOBER 10, 2023
JetBlue will oversee construction of the 230,0000-sq-ft terminal, with Hunt/Moss serving as construction manager at risk.
Autodesk Construction Cloud
DECEMBER 31, 2021
And with good reason: the right insights can improve everything from project cost and timeline accuracy to reducing the risk of lawsuits and disputes, and even winning more business. Or implementing new safety training to mitigate worker injury risk You can then use that knowledge to anticipate and better manage risk for future jobs.
GCP Applied Technologies
FEBRUARY 19, 2020
Concrete materials management. Below are some helpful articles for concrete producers to consider while managing their materials, from overcoming common quality obstacles to dealing with returned concrete. Mitigating risks in concrete production. . . Mitigating risks in concrete production. michael.delros…. Aggregates.
Construction Dive
JANUARY 3, 2019
As construction manager at risk for a new Southwest concourse, the contractor will oversee construction of new boarding gates, connector bridges and more.
ENR Construction
SEPTEMBER 30, 2019
While working within the busy Los Angeles International Airport, contractors delivered this $398-million project under a construction manager-at-risk method, completing it ahead of schedule and on budget.
Autodesk Construction Cloud
AUGUST 3, 2023
And managing the operational maintenance programme of a facility of this size and scope is challenging. By using Autodesk Build , an Autodesk Construction Cloud solution, the French-Swiss airport Basel-Mulhouse-Freiburg can now save 360 days of worker hours when planning its equipment maintenance.
The Constructor
SEPTEMBER 10, 2012
There are four phases of project management which are required to manage projects efficiently on quality, time and costs. Defining and organizing the project: Defining project is the first step in the project management process. Team members monitor and control progress in terms of cost, time, and quality; and manage risk.
Job Order Contracting
MAY 22, 2018
LEAN Job Order Contracting best management practices are critical to assuring optimal outcomes for owners, building users, and construction contractors. Risk mitigation. Airport upgrades. The post LEAN Job Order Contracting Best Management Practices appeared first on 4BT. Contaminated soil disposal. Culvert lining.
Autodesk Construction Cloud
SEPTEMBER 19, 2022
Silver Line Metrorail project leading to the Dulles International Airport. 5: Perform Project Risk Assessment. You should take the time to evaluate all the steps that were used to manage the misstep. The post Damage Control: 5 Ways to Manage Construction Mistakes appeared first on Digital Builder.
Viewpoint Construction Technology
JANUARY 29, 2019
Denver Airport. Al Maktoum Airport, Dubai. Reduce risk and increase safety. Big airports equals big bills. The Al Maktoum Airport in Dubai is a gigantic project! According to thebalancesmb.com , the massive airport is already 21 square foot miles and will become even bigger with an upcoming expansion.
Job Order Contracting
AUGUST 20, 2023
Education, key performance indicators, common terms and definitions, collaborative construction delivery methods, and current, objective, local market granular cost data as well as supporting technology can to be leveraged to enable significant cost savings via signifincant improvements in cost visibility, cost management, and productivity.
Construction Superintendent Magazine
NOVEMBER 11, 2015
Hensel Phelps was recently awarded a construction manager-at-risk contract for the concessions build-out at Austin-Bergstrom International Airport in Austin, Texas. a hospitality, food service and retail company, servicing airports and sports venues across the globe.
Building Information Management
JUNE 28, 2016
Major Risks Facing Public Real Property Owners. I regularly see articles about how great real property owners are, or how the facility management staff performs well, but may be misunderstood. Do real property owners and facility managers actually think they are doing a good job?
The Constructor
SEPTEMBER 10, 2012
WHAT IS PROJECT MANAGEMENT? If you’re managing a project and you want to ensure its success, you need to transform what may begin as a vague concept into a measurable and accountable process that meets your company’s requirements. By managing projects effectively, you generate immense benefits for your company.
Construction Test
MAY 19, 2020
Social distancing will not work in airports, and governments will have to agree international standards before passengers are confident enough to travel, Heathrow Airport Chief Executive Officer John Holland-Kaye said in an interview with Bloomberg TV. ” Heathrow Airport. Photo: iStock.
The Constructor
DECEMBER 20, 2011
Advertisement Hot Topics Recent Topics Most Viewed Most Discussed FOUR PHASES OF PROJECT MANAGEMENT WHAT IS PROJECT MANAGEMENT? Tweet Loading GET LATEST TOPICS IN YOUR EMAIL- SUBSCRIBE NOW. He is the founder of The Constructor and works in a reputed construction company.
Construction Superintendent Magazine
SEPTEMBER 20, 2013
Simultaneously, Gilbane is managing the modernization of Concourse B, a process that is scheduled for completion in April 2015. frontpage'
BD+C
SEPTEMBER 8, 2023
Scott Martin, PE, LEED AP, DBIA Building Team Contractors Designers Designers / Specifiers / Landscape Architects Engineers Facility Managers Architects Building Owners Recently, I was asked to present to a group of aspiring engineers at the Florida A&M-Florida State University College of Engineering.
BD+C
MARCH 14, 2023
Currently, there’s a lack of consistency in how we manage and track housekeeping on jobsites. From hospitals to stadiums, airports to corporate headquarters, and power plants to tunnels and bridges, the important buildings and infrastructure we create help heal, transport, entertain and energize communities. That’s where Spot comes in.
Business Facilities
OCTOBER 17, 2016
An airport of entry (AOE), usually designated with the word “international”, provides customs and immigration services for incoming flights. These services allow the airport to serve as an initial port of entry for foreign visitors arriving in a country. NASHVILLE ASCENDS: A CITY AND AIRPORT FLYING HIGH. military forces.
Autodesk Construction Cloud
JANUARY 14, 2022
Isabel Harlan , Senior Engineer and Project Manager at Hatch LTK , has learned to expect unexpected challenges in engineering. I have a civil engineering background, but with Hatch LTK I have taken the project management path. Walk us through your career and what led you to become a Civil Engineer and/or Project Manager.
Job Order Contracting
JUNE 25, 2018
Real property owners and facilities managers can now efficiently execute their numerous renovation, repair, and minor new construction projects and cost-effectively reduce deferred maintenance levels. Easily Initiate, Manage, and Complete Projects. Track and Manage and Report All Projects Via Simple Cloud Interface.
Job Order Contracting
JANUARY 23, 2019
I first started working with public facilities and physical infrastructure capital planning and management decades ago. was crumbling under the weight of deferred maintenance and poor management. This database is known as the Federal Real Property Profile Management System (FRPP MS). The truth is likely that both are to blame.
Construction Specifier
APRIL 13, 2023
The construction industry faces a myriad of challenges, such as completing projects on schedule, ensuring the quality and safety of products and materials, overseeing the costs so they do not exceed the budget, and complying with corporate environmental and social responsibility standards; all while applying effective risk management at every step.
DebunkTheBIM
JANUARY 1, 2017
A half-a-globe holiday trip on a cheap has its certain characteristics, meaning a lot of airlines and airports have been involved. Most of the real security happens behind the scenes, based science and pseudo-science, on algorithms, risk calculations, tip-offs and simply picking up the guys that tend to be trouble, or something like this.
Building Information Management
OCTOBER 26, 2015
However, multiple studies/reports note that available and proven LEAN best management practices have not been implemented on a widespread basis. and security needs and risk items; ■ System quantities for development, test, and production; ■ Deployment and maintenance plans.
The Constructor
NOVEMBER 11, 2011
Advertisement Hot Topics Recent Topics Most Viewed Most Discussed FOUR PHASES OF PROJECT MANAGEMENT WHAT IS PROJECT MANAGEMENT? RECOMMENDED FOR YOU Building Hong Kong’s Airport Close He is the founder of The Constructor and works in a reputed construction company. All rights reserved.
Job Order Contracting
JULY 26, 2019
The latter is generally excessively costly and may present the risk of fraud if a JOC consultant is involved in JOC Program management. Job Order Contracting BASICS. Purchase of these tools and services however should be done on a specific dollar fee/price basis, and not procured as a percentage of total JOC construction volume.
Autodesk Construction Cloud
AUGUST 15, 2023
From design and VDC professionals to business and project managers, these construction leaders aren't just building structures and facilities—they're shaping our world. Utilizing a data-driven and detail-oriented approach, she guides departmental collaboration and manages the customer experience."
Autodesk Construction Cloud
FEBRUARY 22, 2022
Hear about how they help solve common construction challenges around materials management and work packaging and learn more about their integrations and how they enable information to flow in a project and unlock productivity. Barry Peyton , Business Development and Strategic Partnership Product Manager at Intelliwave Technologies .
Building Information Management
JANUARY 27, 2014
Whether you are cost estimating, designing, managing projects, and/or involved in Integrated Project Delivery – IPD, Job Order Contracting – JOC, and involved any related collaborative construction delivery process… or thinking our it… now’s the time to get more serious, or get on board! just your own!
The Constructor
MARCH 21, 2012
Knowledge of the magnitude of the thermal movement is necessary to evaluate the risk of thermal cracking in situations where large thermal gradients are likely to occur, and to calculate dimensional changes in structures such as bridge decks. Tweet Loading GET LATEST TOPICS IN YOUR EMAIL- SUBSCRIBE NOW.
Autodesk Construction Cloud
APRIL 18, 2022
for airports $20–of actual construction to be put in place. Project delivery matters in these cases, and you want to be able to assume the appropriate risks or make sure your owner is going to share or allocate those risks.”. A lot of that work involves project management software,” remarks Jimmy.
Job Order Contracting
JULY 10, 2017
asset management: coordinated activity established by an organization to monitor, control, and realize value from physical items. Examples: buildings, roadways, dams, bridges, utilities, mass transit, airports, equipment. Examples: buildings, roadways, dams, bridges, utilities, mass transit, airports, equipment.
The Constructor
NOVEMBER 8, 2011
Advertisement Hot Topics Recent Topics Most Viewed Most Discussed FOUR PHASES OF PROJECT MANAGEMENT WHAT IS PROJECT MANAGEMENT? He is the founder of The Constructor and works in a reputed construction company.
The Constructor
JANUARY 29, 2012
This leads to the presentation of an Information Technology IT tool for construction project safety management Total-Safety and, in particular, a module within Total-Safety designed to help construction personnel develop method statements with improved levels of hazard identification.
The Constructor
JANUARY 14, 2012
Advertisement Hot Topics Recent Topics Most Viewed Most Discussed FOUR PHASES OF PROJECT MANAGEMENT WHAT IS PROJECT MANAGEMENT? He is the founder of The Constructor and works in a reputed construction company.
The Constructor
MARCH 18, 2012
MINIMISING THE RISK OF CORROSION: The quality and depth of concrete in the cover zone are all important in minimizing the risk of corrosion as shown in fig. However, in situations where these materials are not cured properly there is a risk of increased carbonation. Tweet Loading GET LATEST TOPICS IN YOUR EMAIL- SUBSCRIBE NOW.
The Constructor
NOVEMBER 8, 2011
Advertisement Hot Topics Recent Topics Most Viewed Most Discussed FOUR PHASES OF PROJECT MANAGEMENT WHAT IS PROJECT MANAGEMENT? He is the founder of The Constructor and works in a reputed construction company.
The Constructor
NOVEMBER 10, 2011
The two former islands that were levelled comprise about 25% of the surface area of the airport’s 12.55 Land reclamation for the airport added nearly 1% to the entirety of Hong Kong’s surface area. The project is the most expensive airport project ever, according to Guinness World Records. km² platform.
The Constructor
JANUARY 14, 2012
Advertisement Hot Topics Recent Topics Most Viewed Most Discussed FOUR PHASES OF PROJECT MANAGEMENT WHAT IS PROJECT MANAGEMENT? He is the founder of The Constructor and works in a reputed construction company.
Expert insights. Personalized for you.
We have resent the email to
Are you sure you want to cancel your subscriptions?
Let's personalize your content