No Longer in the Dark: A Primer on the Distinction between Delay and Disruption Damages in a Construction Dispute
Best Practices Construction Law
SEPTEMBER 24, 2020
According to the Contractor’s expert, the contract established a “baseline schedule … created by the County’s engineer,” which showed a starting date with unhindered access along the area of the road where the utilities were located. Owner-Related Delays. Nevertheless, the Contractor completed its work within the contract time.