Because non-prepriced items have not been competitively bid, their use should be kept to a minimum to ensure the cost effectiveness of the JOC program. Of the 298 job orders recorded in PROGEN (the JOC application), 47 included one or more non-prepriced items. These inconsistent billing practices cost the city an additional $54,037.

article thumbnail

Job Order Contracting – Audit Results

Building Information Management

Because non-prepriced items have not been competitively bid, their use should be kept to a minimum to ensure the cost effectiveness of the JOC program. Of the 298 job orders recorded in PROGEN (the JOC application), 47 included one or more non-prepriced items. These inconsistent billing practices cost the city an additional $54,037.