Job Order Contracting – Audit Results
Building Information Management
MAY 13, 2016
Job Order Contract Audit – City of Tampa JOC Audit – 2010. The Job Order Contract Program Lacks Sufficient Oversight to Ensure Program Effectiveness. In 8 task orders, the non-prepriced tasks represented the majority of the task order’s total cost. to provide renovation work using the JOC process.
Let's personalize your content