Job Order Contracting – Audit Results

Building Information Management

Job Order Contract Audit – City of Tampa JOC Audit – 2010. The Job Order Contract Program Lacks Sufficient Oversight to Ensure Program Effectiveness. In 8 task orders, the non-prepriced tasks represented the majority of the task order’s total cost. From 50% to 75% 5 projects.