BUSINESS REPORT: Maryland — SSA’s New Data Hub Moves Forward In Urbana
Buisness Facilities Contributed Content
AUGUST 29, 2013
The contract’s total cost is about $192 million, according to GSA documents filed online. The new data center will seek LEED Gold certification, and is scheduled to complete construction in late 2014. Bankruptcy Court in Delaware and said it expects the sale to be completed in two to three months. Photo: Thinkstock.com.).