Contractor Submits “Penny Bid” for Rock Removal and Loses in the End
Best Practices Construction Law
MAY 19, 2015
This was an important distinction for the court when reviewing the differing site conditions claim: Celco submitted no evidence suggesting that the character of the rock discovered on site was different, or that the actual unit cost to remove it was greater, by reason of the increased amount or any other concealed condition.