Subcontractor’s Failure to Strictly Comply With Notice Provision Costs $200,000
Best Practices Construction Law
JUNE 21, 2016
shall be deemed a conclusive waiver by the Contractor of any and all claims for damages for delay arising from such condition. ” The appellate court also found that actual knowledge of the delays and claims did not excuse the subcontractor from complying with the the notice requirements of the contract. .”