Digital Dryshack #87: 10 Reasons D.O.D. Schedules get Rejected

Cassell Construction Estimating

firm providing scheduling training in Honolulu last week reminded me of the struggles most midsize contractors face when submitting an Initial Project Schedule (IPS) to NAVFAC or the Army Corps of Engineers. These 2 rules are absolutely non-negotiable: Every Activity but the first (Contract Award) must have a Predecessor.

Schedule 100
article thumbnail

Exciting products and fresh directions

Cassell Construction Estimating

Some rebound in health care, education, and agriculture is forecast for next year, but private development and residential construction is predicted to continue its decline. Therefore the companies with solid presence in public works, and negotiated markets are best-positioned for the current recession.