No Longer in the Dark: A Primer on the Distinction between Delay and Disruption Damages in a Construction Dispute

Best Practices Construction Law

The County entered into an agreement with the Contractor to expand a three-mile stretch of road. The contract allowed for “delay damages” if the Contractor’s request for those damages “is determined to be compensable.”. The Contract. Under the contract, the County was responsible for moving gas, water, and fiber-optic utilities.

Claims 118
article thumbnail

Job Order Contract Execution Guide – Sample Template

Job Order Contracting

project task/line item, a full description in plain English, a unit of measure and a corresponding unit price, including labor, material, and equipment details, and an associated approved contractor coefficient are to be the basis for Contractor compensation. coefficient (reference table of allowable overhead). authorization.

Contract 100
professionals

Sign Up for our Newsletter

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Trending Sources

article thumbnail

#66:  Labor Inefficiency Costs: Who Pays? How Much?

NH Construction Law

Sometimes this unanticipated time/space compression is the owner’s fault, in which case the general contractor/construction manager and its subcontractors will likely be entitled to increased compensation by change order or otherwise -- and to a mechanic’s lien if that increase is not paid. See Town of Bedford v. Brooks , 121 N.H.

Lien 40
article thumbnail

One Awesome Case Discussing The Difference Between Delay and Disruption Damages!

Best Practices Construction Law

The County entered into an agreement with the Contractor to expand a three-mile stretch of road. The contract allowed for “delay damages” if the Contractor’s request for those damages “is determined to be compensable.” The Contract. ” Owner-Related Delays. Sovereign Immunity Argument. .”

Claims 48
article thumbnail

A glossary of terms with reference to Construction Cost Estimating

Construction Cost Estimating

Cost - the value of currency required to obtain a product or service, to expend labor and use equipment and tools, or to operate a business. The crew may also include construction equipment required to execute the work. In construction, the costs of materials, labor, equipment, etc., See also Overhead, Indirect cost.

article thumbnail

A Primer on MasterFormat & Improving Construction Project Collaboration

Building Information Management

Process Equipment Subgroup: Divisions 40 – 49. 00 45 26 Workers Compensation Certificate Schedule. 00 52 00 Agreement Forms. 00 52 13 Agreement Form – Stipulated Sum (design/bid/build or. 00 52 16 Agreement Form – Cost-Plus (design/bid/build or design/negotiate/build). 00 52 00 Agreement Forms.

article thumbnail

A Primer on MasterFormat & Improving Construction Project Collaboration

Building Information Management

Process Equipment Subgroup: Divisions 40 – 49. 00 45 26 Workers Compensation Certificate Schedule. 00 52 00 Agreement Forms. 00 52 13 Agreement Form – Stipulated Sum (design/bid/build or. 00 52 16 Agreement Form – Cost-Plus (design/bid/build or design/negotiate/build). 00 52 00 Agreement Forms.