Footing Bar Bending Schedule (BBS) – Estimation of Steel Quantity
The Constructor
OCTOBER 19, 2018
Bar bending schedule (BBS) of an concrete footing provides the reinforcement details and the total steel quantity required for the footing.
This site uses cookies to improve your experience. By viewing our content, you are accepting the use of cookies. To help us insure we adhere to various privacy regulations, please select your country/region of residence. If you do not select a country we will assume you are from the United States. View our privacy policy and terms of use.
The Constructor
OCTOBER 19, 2018
Bar bending schedule (BBS) of an concrete footing provides the reinforcement details and the total steel quantity required for the footing.
Job Order Contracting
APRIL 29, 2020
Detailed line item construction cost estimating is a prerequisite to obtaining best value outcomes for facilities / built infrastructure repair, renovation maintenance, sustainability, and new construction projects. A locally researched detailed line item construction cost estimating database plays a key role in this regards.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
The Constructor
OCTOBER 19, 2018
The bar bending schedule(BBS) of an R.C.C footing provides the reinforcement details and the total steel quantity required for the footing.
CivilJungle
FEBRUARY 5, 2021
What Is Estimate? The estimated or anticipated cost of the project is an estimate that is commonly calculated well before the project is taken up. The main goal of estimation is to encourage us to always understand the cost of work prior. Appropriate estimation is planned by detailed estimation in specific item wise.
Stok
JUNE 27, 2018
After a successful project kick-off , a solid foundation is required to bring your project into “flow state”. That foundation is a detailed schedule and budget, created and owned by the Project Manager, with input from consultants and contractors, and approved by the Client. Integrate administrative timelines into the schedule.
CivilJungle
MARCH 4, 2022
What Is Estimation of Residential Building? Estimation of a residential building is basically a “ Bottoms Up” or “Prime Cost” which performed an analysis in detail and finally produce a product. Estimation actually calculates all the necessary values with a lower rate and higher amount, this method helps the owner.
Civil Lead
JANUARY 23, 2020
What is Bar Bending Schedule (BBS)? Bar bending schedule is a list of reinforcement bars in a tabular form giving the particulars of bars, the shape of bending with sketches, length of each, total length and total weight. Usually, for each type of RCC work a schedule of bars is usually prepared. Foundation raft, footing etc. -
The Constructor
NOVEMBER 1, 2011
The problem areas, effects in foundation and defects in structure due to those causes are presented here. The problem areas, effects in foundation and defects in structure due to those causes are presented here. Insufficient width of foundation Settlement of foundation occurs due to insufficient distribution of load.
Wolgast Corporation
DECEMBER 6, 2023
Three-Phases to Design-Build Construction: Preliminary Design and Estimating Detailed Construction Drawings and Bidding Construction Step One/Phase I – Preliminary Design and Estimating In this First Step or Phase our Architect develops plans based on a needs analysis meeting with the building owner and representatives for a nominal fee.
The Constructor
AUGUST 16, 2012
Rubble Stone Soling: The rubble stone generally used are of best variety of black trap / granite / basalt or other variety of stone available locally. Tweet Loading GET LATEST TOPICS IN YOUR EMAIL- SUBSCRIBE NOW.
Job Order Contracting
MARCH 26, 2023
Robust Process, Integrated Teams Defined Workflows Validate Cost Data Robust tools and support services are now readily available to support all these foundational requirements. Procurement Workflows A detailed scope of work and an associated detailed line-item estimate is required before any procurement evaluation and award.
Wolgast Corporation
MARCH 19, 2024
The Start In the State of Michigan, the school foundation allowance is intended for instruction and operations of a School District. We typically suggest scheduling a Treasury appointment nine months (or no less than six months) prior to the intended election date. Construction meetings are regularly scheduled normally every two weeks.
The Constructor
NOVEMBER 15, 2011
The following points should he observed while setting out trenches: (i) Profiles, nails, strings and lime are used for Setting out the foundation plan. (ii) 2) The axial lines (center lines) of the trenches are marked with the help of profiles, sighting rails, strings and pegs. (3)
Job Order Contracting
APRIL 25, 2022
Our robust processes and technology deliver a best value solution and a solid foundation for continuous improvement. . Δ Four BT, LLC (4BT) – 4BT has experienced staff to assist any public sector organization in creating, improving, and managing any size or type of JOC Program.
Job Order Contracting
JULY 28, 2023
As a result, FSRM cost estimates and the ability to validate constractor proposal have suffered. The use of generic cost estimating software or spreadsheets are not appropriate for JOC. Sustainment includes regularly scheduled adjustment and inspections, maintenance, and emergency response and service calls for minor repairs.
CivilJungle
FEBRUARY 27, 2021
For load-bearing structure, the foundation plinth area rate per 1 sq.m. For load-bearing structure, the foundation plinth area rate per 1 sqm is 2980, super-structure is 7310 and finishing is 1495. For load-bearing structure, the foundation plinth area rate per 1 sqm is 2980, super-structure is 7310 and finishing is 1495.
Job Order Contracting
JANUARY 22, 2021
The consistent achievement of best value quality, cost, and schedule outcomes requires the strategic and tactical integration of planning, procurement, and project delivery in concert with the core organizational mission. An outline of these and additional components of these proven frameworks is provided below. Sample Workflow.
Construction Cost Estimating
SEPTEMBER 28, 2015
This construction video provides brief guidelines for the design for tank foundations with AFES foundation design software. AFES is a useful software designed for raft foundation. It consists of structural calculation report, construction drawing having bar schedule, material quantities and 3D CAD modeling.
Autodesk Construction Cloud
JUNE 8, 2023
the preconstruction phase), you complete a significant part of the job and create a strong foundation and direction for the remaining work. It’s the most optimal period for identifying issues that may impact cost and schedule. When you stay on top of project planning and design from the beginning (i.e.,
Construction Marketing
SEPTEMBER 9, 2021
Poor deployment of resources – when communication is poor, scheduling and staffing becomes inefficient. For example, workers may not know when and where important tools and machinery are available, and areas of the project that are ahead of schedule will not know to send workers to tasks that are falling behind. Labor Shortages.
Lets Build
NOVEMBER 18, 2022
How many of your construction projects met their initial cost estimates? If that number is more than you care to admit, you’re not alone— McKinsey found that large projects tend to go 80% over budget and take 20% longer to complete than estimated. Unrealistic estimates to win bids. Budgeting and cost overruns.
The Constructor
SEPTEMBER 10, 2012
Organizing projects means defining roles and responsibilities, create a project charter, and develop high-level time and cost estimates. In this phase you assemble your team and assign tasks to individuals, develop a budget for the project, develop a schedule and create a communications plan.
Stok
JULY 29, 2018
The foundation for any successful project is a detailed schedule and budget. stok’s Project Managers first shared tips for creating an accurate Master Schedule. If your client uses outside counsel for legal review of lease and contracts, request a fee estimate to include in your budget. The post Project Foundation Pt.
Construction Cost Estimating
APRIL 28, 2014
The foundation for a successful estimate depends on authentic takeoff of the quantities of the various materials involved in the project. The various elements that lead to an effective cost estimate are as: Labor Hours : Labor hour amounts can be prepared by crew analysis or applied on a unit man-hour basis.
Job Order Contracting
MARCH 4, 2020
While fundamental LEAN elements serve as the foundation, solutions can be tailored to an organization’s individual requirements. Early and ongoing involvement of internal and external teams, inclusive of joint scope and schedule development Reliance upon local, on-site service delivery partners (AEs, builders…).
Construction Cost Estimating
DECEMBER 6, 2017
This construction video provides detailed information on slab reinforcement that is created with bar bending schedule (BBS). Bar bending schedule (aka schedule of bars) belongs to a list of reinforcement bars, a specified RCC work item.
Construction Cost Estimating
SEPTEMBER 25, 2015
One can estimate the proper quantities concerning the concrete and brickwork out of the layout drawings. In case the working drawings and schedules for the reinforcement are unavailable, the estimation should be made on the basis of the predictable quantities.
Construction Cost Estimating
NOVEMBER 3, 2011
Construction Cost Estimating Blog. This feature allows us to easily schedule the type, quantity, etc. With this information we can also begin cost analysis & estimating directly from Revit. Material takeoff schedules list the sub-components or materials of any Revit Architecture family. Join our estimating forum.
Construction Cost Estimating
MARCH 11, 2015
THE ESTIMATING PROCESS FROM A TO Z Here in this cover story we are going to present you the basic details of the estimation. First, we have to download the estimating and budgeting spreadsheet. CUSTOMIZING THE ESTIMATING AND BUDGETING WORKSHEET This is an excel format of spreadsheet. A patience read is necessary here.
Construction Cost Estimating
FEBRUARY 24, 2015
Construction project scheduling for home building projects Construction project scheduling for home building projects has two sides – developing the plan and Using the plan (daily scheduling). Or that you simply have scheduled too several subs on the duty at identical time and they are in every other''s way!
Autodesk Construction Cloud
APRIL 24, 2023
Decisions made using “bad data” are estimated to cost the industry $88.69 With better planning and alignment up front, you’re more likely to mitigate risk and issues that could plague project profitability at later project stages. Take estimation for instance. That’s just factoring in reported rework and direct expenses.
Construction Cost Estimating
OCTOBER 25, 2016
This construction video provides step-by-step guidelines on estimation of Reinforcement with column and footing as per construction drawing. The video will be very useful for foundation design. It is recommended to estimate reinforcement quantity before tendering phase for measuring cost of project or construction work roughly.
CivilJungle
JUNE 27, 2020
For cutting and bending purposes, schedules should be provided as separate A4 sheets and not as part of the detailed reinforcement drawings. • The form of bar and fabric schedule and the shapes of the bar used should be in accordance with BS 8666. • It is preferable that bars should be listed in the schedule in numerical order. •
Construction Cost Estimating
FEBRUARY 23, 2011
Construction Cost Estimating Blog. The Cornerstone of Cost Estimate. The cost estimation is the rapidly growing trend in AEC industry. On the basis of the estimated cost a proper bid will be prepared. A good estimate must start with a complete understanding of scope of work followed by an accurate quantity takeoff.
The Constructor
NOVEMBER 11, 2011
Home News Videos Tips Building Building Bye Laws Building Materials Aggregates Cement Wood Building Tips Buildings Green Buildings Flooring Formwork/Shuttering Paints & Decoratives Skyscrappers Smart Materials Concrete Concrete Admixtures Concrete Cracks Crack Repair Concrete Durability Concrete Properties Concrete Types Fibre reinforced Fire Proof (..)
The Constructor
NOVEMBER 8, 2011
Home News Videos Tips Building Building Bye Laws Building Materials Aggregates Cement Wood Building Tips Buildings Green Buildings Flooring Formwork/Shuttering Paints & Decoratives Skyscrappers Smart Materials Concrete Concrete Admixtures Concrete Cracks Crack Repair Concrete Durability Concrete Properties Concrete Types Fibre reinforced Fire Proof (..)
The Constructor
MARCH 17, 2012
Related posts: Advantages of Precast pile foundation over Cast-in-situ pile foundations? Prestressed Concrete Piles CLASSIFICATION OF PILES LOAD ON PILES NEGATIVE SKIN FRICTION ON PILES Can foundation Piles be welded, if yes what is the welding procedure to be followed?
Lets Build
AUGUST 4, 2023
Free eBook: Quick guide to Lean practices for construction professionals The benefits of using construction project execution software in maximising ROI The project execution phase is the most delicate stage — it lays the foundation for the actual work and sits at the heart of the process. This allows you to work within the budget.
Pro Builder
JANUARY 28, 2022
My January column, “ Measurement Fails, Part I ” laid out the many common obstacles standing in the way of achieving accurate measurements, including estimates presumed or disguised as facts, and ratios based on bad numerators, bad denominators, or both. Remember my proclamation on ratios-—An estimate divided by an estimate is bull$#%@!—which
The Constructor
NOVEMBER 16, 2011
Good foundation soil should be available at responsible depth. Nearness of schools, hospitals, market, etc. are considered good for residential site but these facilities do not carry any significance in the selection site for other public buildings. This aspect saves quite a bit in the cost of the building.
The Constructor
JANUARY 14, 2012
Home News Videos Tips Building Building Bye Laws Building Materials Aggregates Cement Wood Building Tips Buildings Green Buildings Flooring Formwork/Shuttering Paints & Decoratives Skyscrappers Smart Materials Concrete Concrete Admixtures Concrete Cracks Crack Repair Concrete Durability Concrete Properties Concrete Types Fibre reinforced Fire Proof (..)
The Constructor
MARCH 17, 2012
Related posts: Advantages of Precast pile foundation over Cast-in-situ pile foundations? We will discuss here the load carrying capacity of both single pile and group of piles. He is the founder of The Constructor and works in a reputed construction company.
Construction Cost Estimating
JULY 12, 2017
The design of soil or pile supported foundation can be completed without any difficulty. This tool is best suited for for creating the design of foundations for industrial equipment like horizontal exchangers and vessels, vertical vessels or towers, pipe racks and other plant supports.
Rory Woolsey
MARCH 20, 2012
Rory Woolseys Construction Estimating Blog. Construction Estimating One Bite at a Time. The Estimating Process; Get it Right! If you are interested in an expanded discussion on the most crucial step in the estimating process then go back and read my blog on "Scope, Scope, Scope!" Tuesday, March 20, 2012.
Expert insights. Personalized for you.
We have resent the email to
Are you sure you want to cancel your subscriptions?
Let's personalize your content