Tongue Twister: Commander Closes Construction Site for COVID and Contractor Can’t Recover Contract Costs
Best Practices Construction Law
JUNE 21, 2022
62982) involved a contractor who sought to recover $99,076 in operational costs incurred on a construction contract during a two-month period in 2020. 2008), wherein a government contractor sought compensation for being barred from a military base for 41 days following the 9/11 terrorist attacks. APTIM Federal Services, LLC (ASBCA No.