Pre-Bid Documents and Estimates Can’t Be Hidden Behind the Curtain in Disputed Delay Claims

Best Practices Construction Law

12, 2021), the contractor filed suit to recover damages from the City on numerous combined waste water treatment projects. The contractor claimed that the City breached its contract by supplying incomplete and inaccurate contract documents, which allegedly caused delays and a two-year extension to the project completion.

article thumbnail

You Can’t Treat Construction Claims Like Your Grandkids

Best Practices Construction Law

As is typical of a design-build contract, no unit prices for rock excavation were set for because the contractor’s foundation solution is not established at the time of award. During construction, the presence of incompetent rock forced the contractor to use more drilling rigs than anticipated.

Claims 62
professionals

Sign Up for our Newsletter

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

article thumbnail

Careful Contract Drafting Could Mean Recovery of Liquidated Damages and Actual and Consequential Damages

Constructlaw

Contractor) to perform the third phase of this cleanup and remediation. Following a series of disputes and project delays, the Town terminated the Contractor. At the time of termination, the Contractor had performed less than 10% of its scope of work.

article thumbnail

Assignment of Benefits for Contractors: Pros & Cons of Accepting an AOB

Levelset

When a property owner files an insurance claim to cover a restoration or roofing project, the owner typically deals directly with the insurance company. They may not have the funds available to pay the contractor out of pocket, so they’re counting on that insurance check to cover the construction costs. Pros & cons for contractors.

article thumbnail

Gobble Gobble First and Then You Can Put Up the Christmas Tree. Well, Kinda.

Best Practices Construction Law

In the world of construction claims, according to one court, these same rules apply—it is premature to award damages before the claim has been considered and either approved or rejected. I find that should the contractor approve said work then the [subcontractor] shall recover same. In VVM Builders, LLC v. CV195021541S (Oct.

article thumbnail

CBCA Offers Potential Insight Into How Board Will Handle Claims Related to COVID-19

Constructlaw

Department of State , 1 the Board rejected a contractor’s claim for additional costs related to demobilization and remobilization of the job site in Freetown, Sierra Leone, due to an Ebola virus outbreak. 2 The contract included all necessary labor, materials, equipment, and services. In mid-March 2015, PSJV remobilized to the site.

Claims 52
article thumbnail

Severin Doctrine: It's Another Name for "Pass-Through-Plus" Claims

Best Practices Construction Law

A contractor's recovery from an owner for damages suffered by its subcontractor is limited in certain circumstances. The Severin doctrine provides that a general contractor cannot sue an owner on behalf of one of its subcontractors to recover monies due to the subcontractor unless the general contractor is itself liable to the subcontractor.