article thumbnail

Pre-Bid Documents and Estimates Can’t Be Hidden Behind the Curtain in Disputed Delay Claims

Best Practices Construction Law

The contractor claimed that the City breached its contract by supplying incomplete and inaccurate contract documents, which allegedly caused delays and a two-year extension to the project completion. million delay claim included approximately $2.3 In WDF, Inc. City of New York , No. 652478 (N.Y. (Mar. The contractor’s $15.7

article thumbnail

You Can’t Treat Construction Claims Like Your Grandkids

Best Practices Construction Law

The contracting officer denied the claim, and the contractor appealed. Another lesson learned is the importance of “reasonableness” when drafting or submitting claims. The contractor submitted a Request for Equitable Adjustment, alleging that it had encountered a Type I differing site condition—i.e,

Claims 62
professionals

Sign Up for our Newsletter

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

article thumbnail

Are Claim Settlements Producing Unexpected Consequences?

Construction Dive

By Bruce Jervis Claim settlement agreements can be drafted any which way. Sometimes they are drafted with broad, general language. Parties signing claim settlement agreements need to be aware. Sometimes they produce unexpected consequences. The supplier sued the state and settled for a stipulated amount.

Claims 48
article thumbnail

No Free Warranty: Connecticut Court Adopts Correction or Repair Test

Constructlaw

a Connecticut court considered for the first time whether the performance of warranty work tolls the statute of limitations on payment bond claims. s (ALS’s) bond claim because ALS admitted that it last performed non-warranty work on the project more than one year before filing suit, meaning the statute of limitations barred its claim.

article thumbnail

Careful Contract Drafting Could Mean Recovery of Liquidated Damages and Actual and Consequential Damages

Constructlaw

After a bench trial, the court entered judgment in favor of the Town, awarding it liquidated damages as provided in the parties’ contract, but refusing to award actual and consequential damages, finding that the Town was “limited in its claim of damages to those attributable under its liquidated damages provision.” Both parties appealed.

article thumbnail

#135:  Unconscionable Arbitration Agreements

NH Construction Law

“An agreement to arbitrate may be unenforceable if pursuing a claim in arbitration is so cost prohibitive that it prevents a party from vindicating its rights.” ” With that opening sentence, the Texas Supreme Court in Lennar Homes of Texas, Inc. ” Id. That didn’t work in Lim v. TForce Logistics LLC , 8 F.4th

article thumbnail

Severin Doctrine: It's Another Name for "Pass-Through-Plus" Claims

Best Practices Construction Law

The claims were made by the contractor on its own behalf, as well as on the behalf of its subcontractor. The claim was presented by the contractor to the DOT. There is a reason why I call the Severin doctrine a pass-through-plus claim. A well drafted liquidation agreement will generally accomplish this purpose.

Claims 48