article thumbnail

Court Recognizes Day-to-Day Changes Are Compensable Despite Contractual Waivers

Best Practices Construction Law

And yet we see a claim for delays and extras filed at the end of a construction project that challenges these very contract provisions. for breach of contract for nonpayment, claims for delay damages and enforcement of its lien rights. Ultimately, the trial court awarded the subcontractor more than $800k for its claims.

article thumbnail

The Broccoli Incident: Making Sure You Ask for What You Want In Construction Claims

Best Practices Construction Law

Having litigated construction disputes for almost 20 years, the issue of entitlement often turns on whether the contractor properly submitted its claims in accordance with the terms of the parties’ contract. No matter the size of the project, proper documentation will eliminate a number of disputes.

Claims 62
professionals

Sign Up for our Newsletter

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

article thumbnail

What I Learned from My Kids About Delay Claims

Best Practices Construction Law

It almost goes without saying that if you have to pursue or defend a delay claim, you are going to need some evidence (whether by expert or otherwise) to establish or to challenge entitlement to the damages sought. Generally, the delay must affect the critical path of the work to be compensable. Identify the critical delays.

Claims 76
article thumbnail

How To Track Increased Construction Costs For Proving Claims

Best Practices Construction Law

I previously blogged about the importance of using daily reports to prove construction claims. Meeting minutes and internal memoranda concerning the claim should be maintained in order to document attempts to resolve matters with the DOT and its representatives. Schedules , including the as-planned and updates.

Claims 48
article thumbnail

Best Practices for Developing a Contractor’s Request for Compensation

Best Practices Construction Law

My mentor and good friend, Cordell Parvin , has over the years shared with me some great best practices for contractors—whether talking about bid protests, accidents on the jobsite, or filing a claim. Recently, Cordell sent me a list of items that all contractors should review when developing a request for additional compensation.

article thumbnail

What I Learned from My Kids About Delay Claims

Best Practices Construction Law

It almost goes without saying that if you have to pursue or defend a delay claim, you are going to need some evidence (whether by expert or otherwise) to establish or to challenge entitlement to the damages sought. Generally, the delay must affect the critical path of the work to be compensable. Identify the critical delays.

Claims 48
article thumbnail

9 Best Practice Tips for a Schedule Analysis of Construction Delays

Best Practices Construction Law

When savvy contractors face delays on a project, they immediately take steps to provide notice, document, evaluate and plan for recovery from those delays. Generally, the delay must affect the critical path of the work to be compensable. If the delay absorbs the “float” in the schedule, then it is not compensable.